The Federal Government has commissioned a 120MVA transmission substation in Billiri, Gombe State, while upgrading the Gombe transmission facility with additional transformers to expand electricity supply across the North-East.
The Minister of Power, Joseph Tegbe, inaugurated the facilities on Thursday, November 19, 2026, saying the investments would strengthen electricity infrastructure, support businesses and unlock economic opportunities in the region.
The projects add 240MW of capacity at the 330kV level and 176MW at the 132kV level, increasing the network’s ability to transmit and distribute electricity.
Speaking at the Billiri substation commissioning, Tegbe said the 120MVA facility would address longstanding electricity challenges affecting Billiri, Numan and neighbouring communities.
He said reliable electricity remained essential to stimulating economic activities, attracting investments, creating jobs and improving living standards.
The new facility has an installed capacity of 120MVA, equivalent to approximately 96MW. It comprises two 60MVA transformers connected to the existing Gombe-Zabana-Yola transmission line.
According to the minister, the installation would strengthen electricity supply within the Jos Electricity Distribution Company (JEDC) franchise area.
He described the project as part of President Bola Tinubu’s commitment to expanding critical transmission infrastructure and ensuring that inadequate electricity supply did not deny communities opportunities for economic growth.
Tegbe urged residents to protect the facility against vandalism, warning that damage to the installations could deprive the communities of their benefits.
“These equipment you have here are your assets. They’ve been built for you and for your use. So I make a great appeal to you. You must take care of these facilities. Keep these facilities safe,” he said.
The minister commended the Gombe State Government for supporting the project, noting that Governor Muhammadu Inuwa Yahaya had created an enabling environment for investment and infrastructure development.
At the Gombe Transmission Substation, the Federal Government also inaugurated an upgrade that increased transformation capacity from 300MVA to 600MVA at the 330kV level.
The project involved installing an additional 300MVA, 330/132kV transformer and replacing an existing 30MVA transformer with a 100MVA, 132/33kV unit.
The replacement raised the downstream transformation capacity to 220MVA, equivalent to 176MW.
The government expects the upgrade to improve electricity supply to more than 70,000 additional households in Gombe and neighbouring parts of the North-East.
Tegbe said the expanded capacity would accommodate growing electricity demand and extend benefits to other parts of the region, including Yobe State.
Earlier, the Managing Director and Chief Executive Officer of the Transmission Company of Nigeria (TCN), Sule Ahmed Abdulaziz, said electricity demand in Gombe and surrounding communities had outgrown the substation’s previous configuration.
He explained that TCN awarded the upgrade contract in June 2021 and completed it in June 2026.
According to him, the new transformers would provide system operators with greater flexibility while allowing the network to transmit more electricity.
“The new transformers provide our system operators with greater operational flexibility,” Abdulaziz said.
“At the 330kV level, the station now has increased capacity to wheel more power onward. At the 132/33kV level, the larger unit provides the Jos Electricity Distribution Company with increased offtake capacity to serve customers in Gombe.”
He urged residents to protect the installations and report vandalism or suspicious activities to security agencies or the nearest TCN office.
Abdulaziz also called on JEDC to maximise the additional capacity by increasing its electricity offtake to serve more customers.
Meanwhile, Gombe State Governor, Muhammadu Inuwa Yahaya, represented by the Commissioner for Energy and Mineral Resources, Sanusi Ahmed Pindiga, thanked President Tinubu for assenting to the Electricity Act 2023.
He said the Billiri substation would benefit host communities and neighbouring states, while urging electricity consumers to avoid wastage.
Also speaking, the traditional ruler of Tangale Chiefdom and Seriki of Billiri, Alhaji Danladi Sanusi Dalandi, said improved electricity supply would boost businesses, attract investments and create employment opportunities.
He added that the project would improve healthcare, education and other social services, thereby enhancing the quality of life in the area.
📢 Follow National Periscope on WhatsApp
Get breaking news and updates directly on WhatsApp.
Join WhatsApp ChannelPost Disclaimer
All rights reserved. This material and other digital content on this website are not and do not represent the stance of National Periscope but the statements of newsmakers mentioned therein.
For your detailed news reportage... contact the Editor at Joel2oladele@gmail.com






FG Moves To Reverse Nigeria’s $20bn Trade Deficit With China Read more
The Commissioner for Solid Minerals, Hon. Bashir Gegu, has urged Read more
Electric cable thief electrocuted in Edo A middle-aged man was Read more
FG Begins Overhaul of Power Distribution Companies with Pilot Scheme Read more